Applications...

When to Use Unfinished...
bulletWhen the flooring is installed over concrete with humps and/or dips exceeding 1/4" per 10', and the floor cannot be ground down or patched, (if a plywood system or a sleeper system is used, the concern of the humps and dips on concrete is not necessary).
bulletIf "overwood" problems occur from bad sub floor milling.  
bulletIf a stain is required.
bulletIf HG is unsure that the finish or milling on our flooring will hold up due to any "unusual in nature" commercial use.

When to Use Pre-Finished...

bulletWhen dust contamination and/or production time is of concern.  
bulletIf the customer does not want to spend an additional $1.00 to $2.00 per square foot to sand and finish the floor.  If the pre-finished floor throughout the construction process is scratched or damaged, it may be screened and coated with another layer of flooring urethane.

More About Unfinished...

bulletBe advised that unskilled finishers can take 1 to 2 "sandings" out of the life of the floor.  Their finished product most generally will have sander marks from large machines and marks from edge or buffer head.  These may not be noticed until after a coat of finish is applied.
bulletIn general, it takes an extra 5 days for the job to be completed.  For example, in a 3,000 square foot job:
bulletTwo skilled installers can sand about 1,000 square feet a day.
bulletAt the end of the third day, the first coat of finish can usually be applied, depending on job conditions.
bulletOn the fourth day, the second coat of finished should be applied based on the humidity in the building if it is dry enough to screen, (scratch the surface for bonding of next coat).
bulletIf additional coats are required, repeat step 3.  At this time for the final coat, the job site must be dusted free so that the finish is not contaminated with dust of dirt.  No heavy traffic should be allowed for at least 72 hours after the final coat.
bulletIt takes the same amount of time to lay either pre-finished or unfinished flooring.

 